Villagers in Chaiyarit Subdistrict complain about the lack of standards on the road. Opened for less than 2 months, completely destroyed.

--

Date: 21 November 2023, Nation News Team Received complaints from villagers that Paved road connecting Between Road No. 32 or Asia Road The area of ​​Village No. 1, Chaiyarit Subdistrict, Chaiyo District, Ang Thong Province, a distance of over 1 km, is in a damaged condition. and there was a collapse of the road surface along the route. causing cars passing by to be affected until some cars were damaged After receiving the notification, he traveled to the area. to check

However, when we arrived we found the condition of the asphalt road. which connects to Highway 32 or Asia Road to Bang Sala Floodgate, Village No. 1, Chairit Subdistrict, Chaiyo District, Ang Thong Province, a distance of over 1 km, is in a damaged condition. Especially in the left channel, about 1 meter wide, sinkholes formed along the route. until the road surface There is an uneven height and low difference of 5-10 cm. and in some places there are deep cracks. As a result, motorcycles and cars of villagers in the area Those using this route must use caution. Because it may cause an accident. Many cars were damaged. From a car that drives on or climb the point where the collapse occurred

Villagers in Chaiyarit Subdistrict complain about the lack of standards on the road. Opened for less than 2 months, completely destroyed.

From the inspection, it was found that such a road It is a project to widen the shoulder of the alphalt road. Width 1 meter, distance 988 meters, ready to install solar power from Chairit Subdistrict Administrative Organization. Using a budget of 3,300,000 baht (three million three hundred thousand baht) hired a private company. to carry out construction The construction started on May 24, 2023 and the contract ended on September 1, 2023.

Villagers in Chaiyarit Subdistrict complain about the lack of standards on the road. Opened for less than 2 months, completely destroyed.

However, after the construction was completed and open to the public to use the service But in less than 2 months, it appears that the road has been damaged. and was completely destroyed throughout the line. including electric poles, chains, and cells which some points were damaged Many villagers who use the said route said that shortly after it was completed, The road collapsed. until clearly visible Some spots are broken into deep trenches. and collapsed from the original road until it became a level road. This road has only motorcycles. that is used for traveling only I’m afraid there will be an accident. Therefore, we would like the relevant agencies to come and check. Is the construction up to standard? Because in less than 2 months, the road collapsed and was damaged along the entire length.

-